Perry County Route AC
Perryville, MO
Emery Sapp & Sons worked with the Missouri Department of Transportation to pave the two-mile stretch of Route AC highway to allow future expansion of an industrial park. While MoDOT’s project schedule allowed enough time for the contractor to pave the project the following summer, ESS set its sights on completing the project by the end of the year. This was going to be challenging in and of itself and receiving over 12″ of rain during the month of August did not help get the project off to a good start. However, ESS utilized stringless paving operations throughout the subgrade preparation to help get back on track after the weather had started us behind schedule. ESS was able to substantially complete this project approximately 9 months ahead of schedule.
Owner Missouri Department of Transportation
Civil Engineer Missouri Department of Transportation
ESS Role General Contractor
Project Duration 4 months
Self-Performed 85%
Awards 2017 ACPA State Road Paving Award
Scope of Work
Using stringless paving techniques ESS paved the two-mile stretch of highway and shoulders using 39,945 square yards of concrete. Overall excavation quantities exceeded 93,000 cubic yards, embankment equaled 60,594 cubic yards, and 1,183 linear feet of storm sewer utilities were placed.