John Twitty Energy Center
Rail Loop Extension
Springfield, MO
Emery Sapp & Sons were contracted for the construction of a track embankment and sub-ballast, in preparation for the expansion of City Utilities existing rail-served loop track offloading facility.
Owner City Utilities of Springfield
Civil Engineer Olsson Associates
ESS Role General Contractor
Project Duration 5 months
Self-Performed 85%
Scope of Work
This project consisted of clearing 4.06 acres, excavating 15,329 cubic yards, and building 4,380 cubic yards embankment and 7,230 cubic yards sub-ballast required for the preparation of the track. In conjunction with the track embankment, containment embankments were also built.