ESS was recently awarded the Highway 59 project in Watts, Oklahoma. The Oklahoma Department of Transportation proposed a 5-lane roadway with paved shoulders, new curbs and gutters, the replacement of two bridge structures and a variable center turn lane. Our Hutchens asphalt crew will be the go-to guys for their paving needs throughout this $14.4 million project.

ESS was contracted to complete major infrastructure improvements to Highway 59 in Watts, Oklahoma. Working for the Oklahoma Department of Transportation (ODOT), ESS will transform the roadway into a 5-lane highway with paved shoulders, new curbs and gutters, replacement of two bridge structures and a variable center turn lane. ESS drew experts from its internal partner company, Hutchens Construction, to perform all asphalt paving throughout this $14.4 million project.

Owner Oklahoma Department of Transportation

ESS Role General Contractor

Scope of Work

This three-mile long project widened Highway US-59 from two to four lanes and included the demolition and reconstruction of two bridges. Earthwork consisted of 400,000 CY of rock blasting, 350,000 CY, unclassified excavation, and 148,000 SY of lime stabilization. During construction, ESS developed a value engineering (VE) alternative to eliminate a deep box culvert. Our teams replaced it with a more effective drainage design that accelerated the schedule and resulted in cost savings.

Excavation 813,424 CY

Concrete Removal 63,116 SY of asphalt

Underground Utilities 3,168 LF

Base Rock 68,943 Tons

Concrete Paving 7,896 CY