Crossland Construction awarded ESS the full site package contract for the Springfield Sports Complex. Construction began on April 26th, 2021 and is estimated to be finished by the end of the summer. This 52-acre complex will feature 12 full size soccer fields, and one impressive recreational indoor facility. In addition to the $1.83 Million sitework package, ESS was also awarded the asphalt pavement package for this project.
Owner SGF Sports, LLC
General Contractor Crossland Construction
ESS' Role Subcontractor
Start Date April 2021
Anticipated Completion Date July 2021
Scope of Work
ESS employee-owners will begin the comprehensive grading and underground utilities for the Springfield Sports Complex in early May. By the end of the summer, our teams will have moved more than 211,000 CY of dirt, installed 3,700 LF of storm drainage and 22 drainage structures.