Mercy Joplin Clinic

Joplin, MO
Mercy Joplin Clinic

Emery Sapp and Sons were contracted by Mercy and Larry Synder Construction to demolish existing infrastructure and construct a roadway extension from the Joplin Hospital roundabout to the site of the new Mercy Joplin Clinic. In addition to the roadway construction, ESS’s contract included the complete site package and building pad for the new clinic. With the time constraints of the project, the goal was to construct a building pad right away so the building contractor could go to work. Next, all the surrounding site work had to be completed while providing access to the building site for multiple building subcontractors. Project communication and coordination were key to working with the building contractor to keep ESS crews efficient and meet the time schedule for overall completion.

Owner Mercy Health Systems

Developer Pitt Development

General Contractor Larry Snyder Construction

Civil Engineer Olsson Associates

ESS Role Subcontractor

Project Duration 13 months

Self-Performed 85%

Scope of Work

At the new site, ESS was responsible for the site grading package, as well as the installation of underground utilities, storm sewer, base rock, and asphalt paving for the new Mercy Clinic. In addition to the building pad, ESS also built a roadway to connect the new clinic to access roads to the Joplin Hospital.

Excavation & Grading 42,456 CY

Sidewalk 12,736 SY

Curb & Gutter 3,725 LF

Storm Sewer 1,732 LF

Water Line 2,054 LF