Greene County Route 65

MoDOT Numbers J8P0605B & J8P0605D

Springfield, MO
Greene County Route 65 MoDOT Numbers J8P0605B & J8P0605D

This project consisted of widening US 65 to a six-lane highway, with three lanes in each direction, between I-44 and US-60 in Springfield, Missouri. This project included heavy bridge construction and renovation. Demolition and construction of a new bridge over BNSF’s Thayer substation line was built in three stages in order to handle the existing traffic on US-65. Four of the seven bridges required the existing deck girder bridges be widened to accept the additional lanes. Shoring plans were designed for the placement of each of the new concrete bridge decks while allowing traffic to flow under the bridges. Two bridges were complete re-decks over BNSF’s Cuba substation lines. Two large crash walls were also constructed adjacent to the tracks at these locations.

Owner Missouri Department of Transportation

Civil Engineer Missouri Department of Transportation

ESS Role General Contractor

Project Duration 24 months

Self-Performed 80%

Scope of Work

The resulting scope of work included; 67,759 cubic yards of excavation and grading, 20,332 cubic yards of embankment, 33,005 linear feet of storm sewer, and 233,814 square yards of concrete pavement and shoulders.

Bridges 7

Embankment 20,332 CY

Excavation & Grading 67,759 CY

Concrete 233,814 SY

Storm Sewer 33,005 LF