Flint Street Design-Build

Shawnee, KS
Flint Street Design-Build

The Flint Street project was a fast-track Design-Build job. One aspect that made this project stand out was the aggressive schedule. It went from rough sketching plans to final design for utility relocation in just 8 months. There were many overlapping aspects of this project in a compressed schedule. Flint is a two lane asphalt roadway with open drainage ditches on each side located within the public right-of-way. Approximately 36 parcels abut this segment of Flint. This minor residential collector street was selected to be the first new street improvement project in the City of Shawnee Street Improvement Program (SIP). The Flint Street Improvements will also include a section of recreational trail from Johnson Drive south to the location of the Nieman North drainage project.

Owner City of Shawnee, KS

Civil Engineer Shafer, Kline, & Warren (SKW)

ESS Role General Contractor

Project Duration 11 months

Self-Performed 55%

Scope of Work

This project required the complete removal and replacement of the existing pavement. ESS took charge on 15,000 cubic yards of grading and widening, over 16,000 square feet of concrete, 5,000 linear feet of curb and gutter, 21,400 square feet of sidewalks with ADA ramps, and 6,100 linear feet of underground utilities. ESS subcontractors completed 8,900 square yards of new asphalt pavement, LED streetlights, recreational trail, landscaping, signage, and pavement markings.

Concrete 16,400 SF

Sidewalk 21,400 SF

Curb & Gutter 5,000 LF

Excavation & Grading 15,000 CY

Storm Sewer 2,300 LF

Sanitary Sewer 400 LF

Water Line 3,400 LF

CLIENT TYPE

DELIVERY METHOD

MARKET CATEGORY

CORE SERVICES