Breckenridge Park

Plat 1

Columbia, MO
Breckenridge Park Plat 1

Breckenridge Park Plat 1 involved the grading and infrastructure for a 74 lot subdivision on the west side of Columbia, MO. We moved approximately 297,000 CY of material, which also included pre-grading for 59 lots in the next plat. Even with some of the environmental and geological challenges, ESS was still able to bring the project in under budget and on time.

Owner Tompkins Homes & Development Inc.

Developer Tompkins Homes & Development Inc.

Civil Engineer Crockett Engineering Consultants

ESS Role General Contractor

Project Duration 12 months

Self-Performed 95%

Scope of Work

For Plat 1 of Breckenridge Park, Emery Sapp and Sons handled the following; major onsite clearing of 90.8 acres, 297,000 cubic yards of excavation and grading, 12,000 square yards of 6″ concrete and 5,350 square yards of 7″ concrete with 14,090 square feet of sidewalk, a combined 19,120 linear feet of storm, sanitary, and water utilities with 108 storm and sanitary structures, and 7,900 linear feet of electrical trenching.

Excavation & Grading 297,000 CY

Concrete 17,350 SY

Sidewalk 14,090 SF

Storm Sewer 6,215 LF

Sanitary Sewer 7,280 LF

Water Line 5,625 LF