Providence Road Extension, Columbia, MO

Client

City of Columbia

Date

February 2009 to November 2009

Contract Amount

$4,204,757

Project Summary

This project will consist of new street pavement from Vandiver Drive to Blue Ridge Road, construction of a new multi-span bridge over Bear Creek and new sidewalks.

Project Features

  • The total cost for this project is $4.2 million. The project is expected to be completed in the fall 2009. Expanding Providence Road will significantly help with vehicular and pedestrian traffic to offer better connectivity to and from the north part of Columbia.